hit counter script

LG ART COOL LA181HSV5 Engineering Manual page 6

Single zone mirror wall mounted 3/4 to 2 tons
Table of Contents

Advertisement

LG AIR CONDITIONER
TECHNICAL SOLUTION (LATS)
LATS Generates a Complete Project Report
LATS software also generates a report containing project design parameters, cooling and heating design data, system component perfor-
mance, and capacity data. The report includes system combination ratio and refrigerant charge calculations; and provides detailed bill of
material, including outdoor units, indoor units, control devices, accessories, refrigerant pipe sizes segregated by building, by system, by pipe
size, and by pipe segments. LATS can generate an Excel GERP report that can imported into the LG SOPS pricing and ordering system.
Proper Design to Install Procedure
LG encourages a two report design-to-install-procedure. After the
design engineer determines building / zone loads and other details,
the engineer opens the LATS program and inputs the project's
information. When the design is complete, the "Auto Piping" and
"System Check" functions must be used to verify piping sizes,
limitations, and if any design errors are present. If errors are found,
engineers must adjust the design, and run Auto Piping and Sys-
tem Check again. When the design passes the checks, then the
engineer prints out a proj ect "Shop Drawing" (LATS Tree Diagram)
and provides it to the installing contractor. The contractor must
follow the LATS Tree Diagram when building the piping system, but
oftentimes the design changes on the building site:
• Architect has changed location and/or purpose of room(s).
• Outdoor unit cannot be placed where originally intended.
• Structural elements prevent routing the piping as planned.
• Air conditioning system conflicts with other building systems (plumbing, gas lines, etc.).
The contractor must mark any deviation from the design on the Shop Drawing, including as-built straight lines and elbows. This "Mark Up"
drawing must be returned to the design engineer or Rep, who must input contractor changes into the LATS file. (Copy the original LATS soft-
ware file, save and rename as a separate file, and modify all piping lengths by double-clicking on each length and editing information.) Like
the shop drawing, the Auto Piping and System Check must also be run on this new "As Built" drawing. The design engineer or Rep must then
provide the final As Built file to the contractor. The Mark Up version must be compared to the As Built version for the following:
• Differences in pipe diameter(s). If incorrect diameters have been installed, the piping must be changed out. If pipe diameters have changed,
check to see if Y-Branches will also need to be changed.
• Changes to outdoor unit and indoor unit capacities. Capacities changes may impact line length changes.
• Additional refrigerant charge quantity ("Trim Charge"). Trim charge will change if piping lengths and diameters change. The As Built version
must reflect installed piping lengths to ensure correct trim charge.
All documents submitted by the contractor, as well as the Shop Drawing and the As Built Drawing files must be provided for commissioning
purposes. Model and serial numbers for all system components must also be submitted. If the steps previously detailed are not followed, and
all documents are not provided to the LG trained Commissioner, the project runs the risk of not being commissioned and voiding any limited
warranty LG offers on the equipment.
6 | INTRODUCTION
Due to our policy of continuous product innovation, some specifications may change without notification.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. "LG" is a registered trademark of LG Corp.
Figure 2:Example of a LATS Tree Diagram.

Advertisement

Table of Contents
loading

Table of Contents

Uploaded: cache9/manual/3273674/Lg-Art-Cool-La181hsv5.html%3Fpage%3D6.gz