3. ACP operation by using the LG ACCS
Operation switching period
It displays the period for stopping the peak operation. For example, if it is set to 5
minutes period, the air conditioners with the peak operation are switched every 5
minutes, which controls the time for all air conditioners to stop constantly.
The operation switching period can be controlled within the range of 5~15 minutes.
2
Setting the current operation status and the power
Caution: Setting the demand control
Because the demand control is set by the externally connected demand controller, the
items such as desired power, desired operation ratio and operation switching period
can not be set wihin the LG ACCS program.
3-54
ACP
The graph for displaying the current operation status and setting the
power control function is displayed at the left side of the demand
control screen. The operator can use this graph to check the power
when all current installed air conditioners operate 100% and to check
the set target power.