hit counter script

Preparation Of Piping - LG ARUV140LTS4 Installation Manual

Hide thumbs Also See for ARUV140LTS4:
Table of Contents

Advertisement

Preparation of Piping

Main cause of gas leakage is defect in flaring work. Carry out correct flaring work in the following
procedure.
Cut the pipes and the cable
- Use the accessory piping kit or the pipes pur-
chased locally.
- Measure the distance between the indoor
and the outdoor unit.
- Cut the pipes a little longer than measured
distance.
- Cut the cable 1.5m longer than the pipe
length.
Burrs removal
- Completely remove all burrs from the cut
cross section of pipe/tube.
- Put the end of the copper tube/pipe to down-
ward direction as you remove burrs in order
to avoid to let burrs drop in the tubing.
Flaring work
- Carry out flaring work using flaring tool as
shown below.
Indoor unit
Pipe
[kW(Btu/h]
Gas
<5.6(19,100)
1/2"
<16.0(54,600)
5/8"
<22.4(76,400)
3/4"
Firmly hold copper tube in a bar(or die) as in-
dicated dimension in the table above.
Check
- Compare the flared work with figure below.
- If flare is noted to be defective, cut off the
flared section and do flaring work again.
" A "
Liquid
Gas
Liquid
1/4"
0.5~0.8 0~0.5
3/8"
0.8~1.0 0.5~0.8
3/8"
1.0~1.3 0.5~0.8
Copper
Slanted Uneven Rough
tube
90
Pipe
Point down
Bar
Bar
"A"
Copper pipe
Clamp handle
Smooth all round
Inside is shining without scratches.
= Improper flaring =
Inclined
Surface
damaged
Even length
all round
INSTALLATION
23
Reamer
Handle
Yoke
Cone
Red arrow mark
Cracked Uneven
thickness

Advertisement

Table of Contents
loading

Table of Contents